The short answerA commercial project moves through feasibility, design, permitting, preconstruction and procurement, construction, and closeout. Design and permitting often take as long as construction itself. In Washington, cities and counties planning under the Growth Management Act now have default decision timelines of 65, 100, or 170 days for project permits, counted from a complete application. The biggest schedule risks are incomplete design, long-lead equipment, and winter weather, and the most reliable way to shorten a schedule is to bring the contractor in during design.
Owners usually ask how long construction will take. The better question is how long the whole project will take, because the months before the first shovel often decide the opening date. Here’s how a commercial project unfolds, what drives each phase, and where time is won or lost in the Inland Northwest.
The phases at a glance
| Phase | What happens | What drives the schedule |
|---|---|---|
| Feasibility | Zoning, utilities, survey, soils, budget check | Site complexity, utility availability |
| Design | Schematic design through construction documents | Owner decisions, consultant coordination |
| Permitting | Land use review (if needed), building permit | Completeness, review workload, hearings |
| Preconstruction | Final pricing, buyout, submittals, ordering | Long-lead equipment and materials |
| Construction | Site, foundation, structure, envelope, systems, finishes | Weather, inspections, trade coordination |
| Closeout | Final inspections, certificate of occupancy, turnover | Punch list, inspection scheduling |
1. Feasibility and due diligence
Before design gets expensive, confirm the site can do what you need. That means zoning and allowed uses, setbacks and height limits, utility capacity, access, a survey, and a geotechnical report on the soils. Surprises found here are cheap. Surprises found during excavation are not.
2. Design
Design usually runs from schematic design to design development to construction documents. The schedule depends heavily on how quickly decisions get made and how well the architect and engineers coordinate. This is also the best time to bring in a contractor, because pricing and constructability feedback is cheapest to act on while drawings are still moving.
Design for the climate from the start. Snow loads are site-specific in places like Hayden for commercial buildings, and ground snow loads in Coeur d’Alene and Post Falls are 60 and 56 psf. Footings go at least 24 inches deep across the region.
3. Permitting
Washington
Washington’s 2023 SB 5290 reworked the Local Project Review Act. Since January 1, 2025, cities and counties planning under the Growth Management Act use default timelines for project permits:
- 65 days for permits that don’t require public notice
- 100 days for permits that require public notice
- 170 days for permits that require public notice and a hearing
Those timelines start once the application is complete, and jurisdictions can adjust which permits fall into each category. Projects that need a hearing, a rezone, or environmental review take longer, so plan for them early.
Idaho
Idaho has no comparable statewide timeline, so review times depend on each city. Ask Coeur d’Alene, Post Falls, or Hayden for current review times when you plan your schedule.
4. Preconstruction and procurement
Once pricing is final, the contractor buys out the work, issues subcontracts, and processes submittals such as shop drawings and product data. This is where long-lead items get ordered. Electrical gear, rooftop HVAC units, pre-engineered steel buildings, storefront systems, and elevators can all take months to arrive, and late orders are one of the most common reasons openings slip.
5. Construction
Construction typically follows this order:
- Site work and utilities
- Foundations, including any cold-weather precautions
- Structure, whether steel, concrete, or wood framing
- Envelope: roof, walls, windows, and doors to get the building closed in
- Systems rough-in: mechanical, electrical, plumbing, and fire protection
- Interiors and finishes
- Site improvements: paving, landscaping, and exterior lighting
Winter in the Inland Northwest
Winter shapes commercial schedules here. The City of Spokane’s snow season runs from November 15 to March 15, and Coeur d’Alene averages close to 70 inches of snow a year. Concrete can be placed in cold weather with heated enclosures, blankets, and adjusted mixes, and Coeur d’Alene publishes a cold-weather concrete procedure, but it costs more and moves slower. Getting foundations in and the building closed in before the hard freeze is often worth more than any other scheduling decision.
6. Closeout
Final inspections, a certificate of occupancy, and turnover close the project. A good closeout package includes as-built drawings, operation and maintenance manuals, warranties, and training for your facilities team. Leave time in the schedule for final inspections and corrections, because you can’t open without the certificate of occupancy.
How to shorten the schedule
- Involve the contractor during design to catch cost and constructability problems early.
- Make decisions on time. Late owner decisions ripple through design, permits, and procurement.
- Submit complete permit applications. In Washington, the review clock doesn’t start until the application is complete.
- Order long-lead items early, sometimes before the permit is issued.
- Ask about early site or foundation permits where your jurisdiction allows them.
- Plan around winter so foundations and the building envelope are done before the coldest months.
Planning a commercial project in Spokane or north Idaho? Tell us about it and we’ll help you build a realistic schedule.
Frequently asked questions
How long does a tenant improvement take compared with a new building?
Tenant improvements are usually much faster because the shell, site, and utilities already exist. The schedule is driven by design, permits, and lead times for items like HVAC equipment, storefronts, and finishes.
Can construction start before the building permit is issued?
Sometimes. Some jurisdictions allow early grading or foundation permits so site work can begin while the full building permit is in review. Ask the permit office early if your schedule depends on it.
Can you pour concrete in a Spokane or Coeur d'Alene winter?
Yes, with cold-weather precautions like heated enclosures, blankets, and adjusted mixes, and following any local procedures. Coeur d'Alene's Building Services department publishes a cold-weather concrete procedure. Winter work costs more and moves slower, so schedules usually try to get foundations in before the hard freeze.
What is a certificate of occupancy?
It's the building department's approval to use the building after final inspections. You can't legally open or move in without it, so the closeout schedule should leave room for final inspections and corrections.
Sources
- Washington Department of Commerce: Local project review and SB 5290
- MRSC: SB 5290 development timelines
- RCW 36.70B.080: Development regulations and permit timelines
- City of Coeur d'Alene: Building Services standard operating procedures
- City of Spokane: Snow response operations
- City of Hayden: Building department design criteria
This guide is general information, not legal or engineering advice. Rules change, so confirm current requirements with the city, county, or state before you design or sign a contract. Last reviewed November 25, 2026.


