The short answerYour building permit comes from whichever city or county has jurisdiction over the property, not from the town in your mailing address. Inside city limits, apply to the city: Spokane, Spokane Valley, Liberty Lake, Coeur d'Alene, Post Falls, or Hayden. Outside city limits, apply to Spokane County Building & Planning in Washington or Kootenai County Community Development in Idaho. In Washington, cities and counties planning under the Growth Management Act now work to default decision timelines of 65, 100, or 170 days for many project permits, counted from a complete application.
Permits are where many projects lose their first month. Most of that time goes to two avoidable problems: applying to the wrong office and submitting an incomplete application. This guide covers who issues permits across the Spokane and Coeur d’Alene area, how to tell which office applies to your property, and what to expect once you apply.
Who issues permits, by city
The office depends on whether the property sits inside city limits.
| Where the property is | Permit office | Notes |
|---|---|---|
| City of Spokane | City of Spokane Permit Center, City Hall, 808 W. Spokane Falls Blvd. | Separate permits for plumbing, mechanical, and electrical |
| Spokane Valley | City of Spokane Valley Permit Center, City Hall, 10210 E. Sprague Ave. | Sewer permits come from Spokane County |
| Liberty Lake | City of Liberty Lake Community Development | City publishes its own design criteria |
| Unincorporated Spokane County | Spokane County Building & Planning | Covers areas outside city limits |
| Coeur d’Alene | Coeur d’Alene Building Services, City Hall, 710 E. Mullan Ave. | Publishes procedures, including cold-weather concrete |
| Post Falls | City of Post Falls Building Division | Commercial wind loads set by calculation |
| Hayden | City of Hayden Building Department, 8930 N. Government Way | Snow loads differ north and south of Miles Avenue |
| Unincorporated Kootenai County | Kootenai County Community Development, 451 N. Government Way | Snow load zones A through D |
How to tell which office applies
Don’t go by the mailing address. Plenty of properties outside Spokane’s city limits have a Spokane address, and the same is true around Coeur d’Alene. The City of Spokane recommends checking a parcel on Spokane County’s SCOUT property dashboard, which shows the jurisdiction and a lot of other useful information. In Kootenai County, the county’s parcel tools and the cities’ zoning maps answer the same question.
If a property sits right at a city boundary, call the permit office before you design anything. Zoning, setbacks, utility connections, and fees all follow the jurisdiction.
What usually needs a permit
The specifics vary by jurisdiction, but in general:
- New buildings and additions always need a building permit.
- Structural changes like removing or moving a load-bearing wall need a permit and usually engineered beam sizing.
- Plumbing, electrical, and mechanical work usually needs its own permit. In Washington, many electrical permits come from the Department of Labor & Industries unless the city runs its own program, and in Idaho some trade permits come from the state.
- Decks, retaining walls, fences over certain heights, pools, and detached structures often need permits depending on size and height.
- Cosmetic work such as paint, cabinets in the same location, and most flooring usually doesn’t.
Spokane Valley’s residential permit page is a good example of how specific these lists get. It covers new homes, duplexes, garages, pole buildings, decks, pools, spas, and fences.
What to expect on timelines
Washington
In 2023 the Washington legislature passed SB 5290, which changed the Local Project Review Act. Since January 1, 2025, cities and counties planning under the Growth Management Act have default decision timelines for project permits:
- 65 days when no public notice is required
- 100 days when public notice is required
- 170 days when public notice and a hearing are required
The clock starts once the application is determined to be complete, and jurisdictions can adjust which permits fall into each category. The practical lesson is that a complete submittal is the fastest way through.
Idaho
Idaho doesn’t have an equivalent statewide timeline law for building permits, so review times depend on each city’s workload and the complexity of the project. Ask the permit office for current review times when you apply.
Design criteria change by city
Each jurisdiction publishes climatic design criteria, and they aren’t identical. Coeur d’Alene lists a 60 psf ground snow load, Post Falls 56 psf, and Hayden 60 or 70 psf depending on which side of Miles Avenue the lot is on. Frost depth is 24 inches across the region. Drawings that use the wrong values get sent back, so check them before plan review. Our snow load and frost depth guide has the full table.
How to avoid permit delays
- Confirm the jurisdiction before design starts.
- Use the right design criteria for that city or county.
- Submit a complete package. That usually means a site plan, foundation plan, floor plans, elevations, sections, structural details, and truss specifications.
- Answer correction letters quickly. Review clocks generally pause while the applicant is working on corrections.
- Line up trade permits early so they don’t hold up inspections.
We handle permit submittals as part of every project. If you’re not sure where to start, tell us about your project and we’ll sort out the path.
Frequently asked questions
Does a Spokane mailing address mean my property is in the city of Spokane?
Not necessarily. Many properties outside city limits use a Spokane mailing address. The City of Spokane points owners to Spokane County's SCOUT property dashboard to confirm which jurisdiction a parcel falls under.
Do I need a separate permit for electrical and plumbing work?
Often, yes. The City of Spokane, for example, requires separate permits for plumbing, mechanical, and electrical work. In both states, some trade permits come from the state rather than the city depending on location, so check before you start.
How long does a building permit take in Spokane?
It depends on the project and how complete the application is. For land use and other project permits, Washington's 2023 law (SB 5290) sets default decision timelines of 65, 100, or 170 days after an application is complete. Simple residential building permits are often faster, and incomplete applications are the most common cause of delay.
Does a remodel need a permit?
Cosmetic work like paint, trim, and most flooring usually doesn't. Structural changes, new or relocated plumbing, new electrical circuits, and mechanical work usually do.
Sources
- City of Spokane: Permit Center
- City of Spokane: Residential permit process
- City of Spokane: Residential building review
- City of Spokane Valley: Permitting
- City of Spokane Valley: Residential building permits
- City of Liberty Lake: Construction design criteria
- City of Coeur d'Alene: Building Services
- City of Post Falls: Current codes and design criteria
- City of Hayden: Building department design criteria
- Kootenai County: Residential building guide
- Washington Department of Commerce: Local project review and SB 5290
This guide is general information, not legal or engineering advice. Rules change, so confirm current requirements with the city, county, or state before you design or sign a contract. Last reviewed November 25, 2026.